We are pleased to report our project in Long Sutton is progressing on track. The new bricks and roof tiles have been successfully matched with the existing materials to create a harmonious look. The windows and sliding doors are due to be installed next week, which will enable the internal works to start.
The key tasks will include the installation of the new kitchen and the removal of the existing rear wall to connect the kitchen and extension into an open plan space. We are looking forward to completion in the coming weeks. The work is being undertaken by Marshall and Mace.